Jan. 27 - Feb. 23: Repair plan design and execution
Feb. 23 - March 13: Final phase of excavation begins
March 16 - April 24: Grease interceptor design/repair plan
April 6 - June 1: Finalize plan to restore permanent power to building
April 29 - July 15: Grease interceptor repair work (projected)
June 10: Underground utility work complete
June 18: Substantial completion/final inspections complete
July 20: Thunder Vista administrators return to building